Ongoing
Projects

Crafting Quality, Inspiring Innovation - See Our Projects in Motion

MV STELLA BEAUTY
ME T/C Overhauling

Date:August 2024
Duration: 24 hrs
Port: Colombo

  • Fully overhauled TC cartridge at their workshop, employing ASH BLASTING techniques for thorough cleaning of the turbine shaft, compressor side, and turbine wheel side.
  • Used chemical cleaning methods for all other parts, ensuring high maintenance standards.
  • Conducted dynamic balancing post-overhauling for optimal performance.
  • Managed the entire scope, including the supply of SS fuel oil ball valves and other necessary materials.
MSC JUANITA F
AFT Port Mooring Winch Leaking Hydraulic Tray Repair

Date: May 2024
Duration: 12 hrs
Port: Colombo

  • Addressed an urgent hydraulic tray oil leak from the AFT Port side mooring winch, which was spilling onto the deck.
  • Proposed a swift repair solution involving opening the gearbox side cover and replacing the hydraulic tray’s steel plates.
  • Completed the repair within 12 hours to prevent any delays in the vessel’s trading schedule.
MSC RICCARDA II
LT Coolers Pipelines Renewal

Date: May 2024
Duration: 24 hrs
Port: Colombo

  • Identified seawater inlet and outlet pipes requiring renewal for LT Coolers 1 & 2.
  • Isolated the coolers prior to starting any work to ensure safety and efficiency.
  • Removed leaking pipes and templated new pipes for precise replacement.
  • Completed final welding on the templated pipes, ensuring a secure fit.
MSC DIYA F
ER VAF Flow Meters Installation

Date: June 2024
Duration: 14 hrs
Port: Colombo

  • Successfully installed flowmeters for multiple systems, including the main engine fuel oil line inlet, AUX boiler fuel oil inlet and outlet, and AUX generators fuel oil inlet and outlet.
  • Managed the full project scope, ensuring accurate measurement and monitoring for efficient fuel management.
  • All installations were completed to high standards, supporting optimal system performance and operational reliability.